Waterloo Railway Station Patent Glazing
Major 28,000 sq/m refurbishment
Project:
Network Rail ; Regeneration Programme for Waterloo Station. Roofing Refurbishment
Supplier:
Lonsdale Metal Company Ltd.
Product:
SkyGard
Installer :
Kelsey Roofing Industries Ltd
Design Engineer :
Stephen Frankham Associates
Main Contractor:
Amec Capital Projects
Lonsdale was definitely the right choice for the job. The system’s inherent flexibility & tolerance gave us a faster installation than we could have achieved with the linking panel type products currently available - Roy Conway, Project Manager, Amec Capital projects.
The original Waterloo station was opened by LSWR in July 1848 and for several years expanded & developed. A complete rebuilding programme was carried out between 1900 to 1922, but it was to be another seventy years or so until any further major changes were made with the building of the Eurostar terminal in the 1990s. Despite this very modern addition featuring an upto the minute, bolted glass roof, the mainline station was in a sorry state of repair.
The transverse ridge & furrow roof construction was designed by J.W. Jacomb-Hood & his successor A.W. Szlumper and measured 520ft x 540ft on plan covering 19 platforms.
This is an area equivalent to five football pitches and is 28,000 sq/m using today’s metric equivalent.
Serving the busy Southcoast mainline route
into London, the station copes with thousands
of passengers a week & hundreds of trains
all of which have taken their toll on the
station environment and not least the huge
glazed roof.
Years of toll on the patent glazing
Over the years, repairs had been carried out on
an ad-hoc basis creating a patchwork of
different glass, various glazing bars and even
‘temporary’ timber panels which had long ago
been overlooked for replacement. Fortunately,
the original steelwork remained in good
condition despite being in need of blasting &
repainting. The ‘patchwork’ of repairs had to go
and a whole new patent glazing system with
modern glass be installed.
Over 28,000sq/m of glazing to be replaced with the station fully operational
Although the layman may mistake the roof’s
nine barrels to look the same, each one varies
in size as they were built in-situ approaching
one hundred years ago. The roof covers
nineteen platforms all of which had to remain
open and functioning for the duration of the
contract with minimum inconvenience to
passengers or train running times.
Amec’s solution was to suspend a ‘crashdeck’ from the steel roof trusses immediately under the glazing allowing contractors to remove old materials & carryout the new installation. A rolling rig was constructed enabling contractors to slide a set of multiple platforms under the curved roof trusses from one end of the roof to the next without having to take down traditional style scaffolding and set up again each time they moved to a new area. Tony Ingram, Roofing Construction Manager for Amec, comments ‘Passengers have only been vaguely aware of something going on overhead, most people don’t know we’re here’
Such an operation needs a ‘rapid-fix’ patent
glazing system
A flexible system was essential which would
accommodate the tolerance and variance of
the site conditions. A simple, easy to handle
product was required. Various options from
all the major manufacturers were considered,
but ‘a few millimetres either way on a linking
panel system for example, would cause major
problems’ states Roy Conway, Amec Project
Manager. ‘We settled for Lonsdale due to the
systems flexibility and ‘forgiving’ nature from the
installation point of view.’ Despite SkyGard
being a tried & tested product, Lonsdale had to
develop specially extended fixing brackets to
permit ventilation at the bottom of each tier of
glazing. This was to allow air-circulation without
undue ingress of water from driving rain, so diesel exhaust could escape, carrying with
it dirt & grime detrimental to the to the glass & aluminium system. Although a polyester
powder paint finish had been considered, this was deemed unnecessary from both an
appearance and performance point of view due
to the Lonsdale twenty five year warranty. The
mill finish option will save the client millions of
pounds as a painted finish would require regular
cleaning to maintain warranty agreements.
To complete the installation 6.4mm laminated
glass was fitted, having been specially cut to
size by The Dorset Glass Company, Poole using
state of the art computer aided machinery.
Swift solution on target to finish Spring this
Year
Roofing contractor, Kelsey Roofing, have kept
their promises and consistently delivered on time. Currently, completion is due for Spring
2003. Steve Arthurs, Project Manager for Kelsey Roofing says, ‘We have made surprising progress with the Lonsdale system as metre for metre we are glazing in two thirds of the time what we were able to achieve during our last major station at Glasgow Central’
Richard Burgess, Sales &
Marketing Director for Lonsdale
comments, ‘ We are delighted
Lonsdale has made a difference
and Waterloo is excellent
testimony to what our design &
fabrication team can achieve.
However, all credit to Kelsey
Roofing, as their excellent
organisation of this contract &
professionalism has made it
easier for us to ensure continuity
of supply.’
Lonsdale offer a RIBA approved CPD seminar ‘Letting light in, keeping weather out’ – An introduction to Patent Glazing
|